What are dayworks in construction, and when are they paid?

Daywork values work using recorded labour, materials and plant under the applicable contract rules. A signed sheet may confirm resources used without agreeing entitlement, rates or the final price.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

Daywork values work by the resources that went into it, not by measuring it. You record the labour hours, the plant hours and the materials used on an item of work. Each is priced at the daywork rates in your contract, or at cost, with percentage additions for overheads and profit.

Check when your actual contract permits daywork, including any agreed daywork instruction. Some valuation rules reserve it for work that cannot properly be measured; that is not a universal rule across every form. Follow the applicable sheet, timing and checking requirements.

Three things follow from that. A signature's effect depends on its wording, authority and the agreement. It may confirm resources without agreeing entitlement or rates. An unsigned sheet can still have corroborating diaries, payroll, hire records and instruction evidence. And daywork you submit for work that could have been measured is usually valued as measured work instead.

So raise the sheet the same day, get it signed the same day, and write on it why the work could not be measured.

Our Variations and compensation events connects authorised daywork with the labour, materials, plant and agreed valuation basis.