Keep the changed work separate in your costs

Timesheets that mix changed work with base scope make cost allocation harder and increase the need for corroborating evidence. Book labour, plant and materials to the variation reference every day, while the people who know are still on the job.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

A variation valued on cost needs the cost. That cost lives on timesheets written by people who had no reason to split it. The gang did 8 hours on Tuesday, half on the change and half on the base scope, and the sheet just says 8. A month later nobody can say which half was which.

The other party sees a claim for hours that could have gone on work already paid for, and refuses it. A later reconstruction may be possible from other reliable records, but must be labelled honestly. Daily reference coding gives a clearer starting point; the actual valuation rules still determine how those costs are used.

How do I do it?

  1. Add a reference column to the timesheet, the plant sheet and the materials order, and make it compulsory.
  2. Tell your supervisors the reference on the day a variation is confirmed, and which work belongs to it.
  3. Book the hours, plant and materials to the reference daily, and have the supervisor initial the sheet.
  4. Check the variation bookings weekly against the job total, so you catch a missed day while you can still correct it.