It should name the instruction, say what changed, show the value and its build-up, and ask for a reply by a set date.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
A variation claim letter should name the instruction, say what changed, show the value and its build-up, and ask for a reply by a set date. A variation claim letter, or claim form, puts one change and its price formally to the other party. Keep each letter to one variation, or to a group of linked ones.
Set it out in this order. First, the instruction: who gave it, when and how, with the written instruction or your confirmation attached.
Second, what changed: the agreed contract scope, the work now required, and the drawings that show the difference.
Third, the value: the sum, the valuation rule in your contract you used, and the measurements, rates or daywork sheets behind it.
Fourth, time: identify the programme effect and check whether a separate time notice is already due. Give required notices within their actual periods, without waiting for the valuation letter.
Fifth, the clause: name the notice or valuation clause you rely on, and meet any period it sets.
Last, the ask: the sum to add to your next application, and a date for a reply.
Keep it factual. Evidence strengthens a letter, and threats and adjectives weaken it. Send it by the method your contract sets for notices, and keep proof it arrived. A letter does not make an unsupported sum payable, and silence is not usually agreement.
Our Variation Recovery service drafts these letters in your name and presses each variation to agreement.
Support the letter with a variation register
Attach the relevant lines from the variation register. For each item, identify the instruction, required notice, valuation basis, supporting records and application reference.
Keep changes in scope separate from disagreements over measurement or rates. Explain how the instruction affected your work and how you priced that effect. A generic reservation of rights does not replace a specific notice required by your contract.
To have each variation claim written, valued and pressed in your name, see our Variation Recovery service.