Skip to content

Make the assessor respond in writing

A written reason for cutting your variation gives you something to argue with, and a bare figure gives you nothing. Ask for the assessment against your build-up, line by line, in writing.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

A variation certified at nil with no explanation leaves you nothing to answer. You cannot tell whether the other party disputes the instruction, the quantity, the rate or the arithmetic. So your next application repeats the same figure and gets the same nil, and months pass.

A written assessment, line by line, turns that silence into a position. Perhaps it accepts the instruction but not the hours, or the hours but not the rate. You can prove or concede each of those. A written reason given now is also one it has to stand behind later. An undervaluation with reasons is a negotiation. One without reasons is just a smaller number.

How do I do it?

  1. Write the same week whenever a variation is certified below the sum you applied for. Ask for the assessment against your build-up, line by line.
  2. Ask which of the instruction, the quantities, the rates and the records are disputed, and why.
  3. Write again if the reply is a bare figure, and note in your next application that no reasons have been given.
  4. Answer each reason with the record that meets it, and concede the ones you cannot support, so the gap narrows every month.

Our Variation Recovery sets out the disputed assessment item by item so differences in scope, quantities and rates can be answered.

Browse changes and extra costs in the Library

Browse the Library