Rate build-up template

Build a unit rate from labour, material, plant and other priced inputs, with quantities and source references.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Use a consistent output unit. Record waste, productivity and the treatment of overhead and profit explicitly; keep supplier quotations dated.

Rate build-up template

Use a consistent output unit. Record waste, productivity and the treatment of overhead and profit explicitly; keep supplier quotations dated.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Rate build-up template

Scroll across if needed to read the whole record. A dash means no value has been entered.

Rate build-up template: completed fictional example
Output / resourceQuantity per output unitInput unitUnit cost (£)Cost per output (£)Source / assumption
1 m² partition / labour0.75hour£30.00£22.50Labour cost L-01; assumed productivity 0.75 h/m²
1 m² partition / board2.1m²£8.00£16.80Supplier Q-14; includes 5% board waste
1 m² partition / framing and fixings1set£10.00£10.00Supplier Q-15
1 m² partition / plant allowance1m²£1.70£1.70Hire allocation H-01

The example direct rate is £51.00/m² excluding VAT, overhead and profit. Add those separately where the pricing basis permits.

Understanding your results

The example direct rate is £51.00/m² excluding VAT, overhead and profit. Add those separately where the pricing basis permits.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.