Price change calculation

Compare baseline and current input prices and calculate an adjustment using the agreed eligible proportion.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Record the contract provision, base date, current date and comparable source. An observed price increase is not automatically recoverable.

Price change calculation

Record the contract provision, base date, current date and comparable source. An observed price increase is not automatically recoverable.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Price change calculation

Scroll across if needed to read the whole record. A dash means no value has been entered.

Price change calculation: completed fictional example
Item / sourceQuantityBase unit price (£)Current unit price (£)Eligible proportionCalculated adjustment (£)Contract basis / status
Steel sections / supplier Q-01 and Q-1810£800.00£920.00100%£1,200.00Illustrative agreed price adjustment for 10 tonnes
Board / supplier Q-02 and Q-19500£8.00£9.000%£0.00Fixed-price item; no adjustment basis identified

Eligible proportion is 1 for 100% and 0 for none. The £1,200 example adjustment assumes an express agreed basis; it is not a statutory escalation entitlement.

Understanding your results

Eligible proportion is 1 for 100% and 0 for none. The £1,200 example adjustment assumes an express agreed basis; it is not a statutory escalation entitlement.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.