Defined Cost is a contractual calculation using specified cost components. It is not simply every cost your business incurred.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
Defined Cost is a contractual calculation using specified cost components. It is not simply every cost your business incurred. Start with your NEC contract's form, edition, main option, Contract Data and amendments. The full Engineering and Construction Subcontract has Options A to E; do not import an ECC Option F definition into it.
NEC4 uses the Short Schedule of Cost Components for A and B and the Schedule of Cost Components for C, D and E. The applicable rules may use specified rates as well as expenditure, and cost-based options also require checks for Disallowed Cost. NEC's explanation of Defined Cost highlights an important change from NEC3: NEC4's schedules include amounts due for subcontracted work, including under A and B. An old instruction to rebuild every lower-tier quotation as direct labour and plant can therefore be wrong. Check the equivalent wording in your own contract.
Build a schedule connecting each item to its permitted component, quantity, rate or cost record. Separate actual and forecast assessment using the contractual dividing date, then calculate the Fee. Your cost schedule should show the calculation and supporting records. It does not decide which costs qualify.
Our Variations and compensation events identifies the applicable cost schedule and evidence behind each component.