Measured mile comparison

Compare labour productivity in comparable unaffected and affected work, with the selection and adjustment basis visible.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Choose genuinely comparable work and record differences in scope, team, location and conditions. Validate the comparison before attributing any difference to an event.

Measured mile comparison

Choose genuinely comparable work and record differences in scope, team, location and conditions. Validate the comparison before attributing any difference to an event.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Measured mile comparison

Scroll across if needed to read the whole record. A dash means no value has been entered.

Measured mile comparison: completed fictional example
Work sampleOutput (m²)Actual hoursHours per m²Baseline hours per m²Expected hoursExcess hoursEvidence / comparability
Unaffected Level 12001000.50.51000Same partition type and team; D-01 to D-05
Affected Level 21601200.750.58040Same specification; access interruptions D-10 to D-14

The example shows 40 excess hours against the selected baseline. It does not prove that all 40 hours were caused by a compensable event. Explain adjustments and other causes.

Understanding your results

The example shows 40 excess hours against the selected baseline. It does not prove that all 40 hours were caused by a compensable event. Explain adjustments and other causes.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.

If you need help preparing or reviewing the project records, our quantity surveying services explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.