Measured-mile analysis compares productivity on sufficiently similar work during less-affected and disrupted periods. It helps investigate lost productivity; it does not establish liability by itself.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
The SCL Delay and Disruption Protocol discusses measured-mile analysis among disruption assessment methods. A comparison needs reliable outputs and resource records, with differences in conditions and other causes considered.
For illustration, 100 units in 200 labour hours gives a baseline of two hours per unit. At that rate, 80 units would need 160 hours. If they actually take 240 hours, the unadjusted difference is 80 hours. At an assumed £30 per hour, that is £2,400 to investigate, not an automatic recoverable loss.
Check gang composition, work type, access, learning, overtime and the claiming party's own performance before drawing conclusions. Explain adjustments and uncertainty. Where no fair comparison exists, choose a supportable alternative rather than manufacture a baseline.
Delay and disruption cost recovery tests the records behind the productivity comparison and separates the calculated difference from the amount attributable to a compensable event. Read the practical disruption problem for the evidence needed before valuing a claim.
Sources
- Delay and Disruption Protocol, 2nd edition, February 2017. Society of Construction Law.