Labour and plant allocation record

Record planned hours, productive work, interruptions and redeployment against the actual location and output.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Use contemporaneous timesheets and site records. Allocate all paid hours once, including redeployment and non-productive time.

Labour and plant allocation record

Use contemporaneous timesheets and site records. Allocate all paid hours once, including redeployment and non-productive time.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Labour and plant allocation record

Scroll across if needed to read the whole record. A dash means no value has been entered.

Labour and plant allocation record: completed fictional example
Date / teamPaid hoursProductive hoursRedeployed hoursIdle hoursHours checkOutput / evidence
7 Oct / 4 installers321688020 m² partitions; D-07 and TS-07
8 Oct / 4 installers322408030 m² partitions; D-08 and TS-08

The hours check should be zero. Idle hours do not by themselves establish a recoverable loss or a delay to completion.

Understanding your results

The hours check should be zero. Idle hours do not by themselves establish a recoverable loss or a delay to completion.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.