A new form sent from the office gets dropped, but the records your site already keeps for wages and plant keep going. Add what the contract needs to those sheets and photos, instead of adding new paperwork.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
A new form competes with everything the site already does, and the site wins. The foreman fills it in for a fortnight, the job gets busy, and the form stops. Meanwhile the site produces records every day without being asked: allocation sheets for wages, day sheets for plant, photos on WhatsApp. They keep going because somebody needs them to get paid or to do the job. Adding the detail the contract needs costs a column, not a new routine, and a column survives the busy weeks.
How do I do it?
- Spend a day on site listing what your people already write down or photograph, and who does it.
- Compare that with what the contract and a claim would need, and mark the gaps: usually a location, a cause and a reference number.
- Add the missing fields to the sheets you already use, and show each person the one extra thing to write.
- Save the WhatsApp photos to the project folder every week, with the date and area, instead of asking people to stop using the group.