Delay event and EOT submission record

Assemble the event chronology, notice record, programme comparison and supporting evidence for a time assessment.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Identify the relevant contractual ground and affected completion obligation. Distinguish observed interruption from its assessed effect on completion.

Delay event and EOT submission record

Identify the relevant contractual ground and affected completion obligation. Distinguish observed interruption from its assessed effect on completion.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Event and notice

Scroll across if needed to read the whole record. A dash means no value has been entered.

Event and notice: completed fictional example
RecordCompleted exampleSource / status
EventLevel 1 access unavailable 7–8 OctAL-07/08 and D-07/08
NoticeN-01 issued 8 Oct; exact content and receipt retainedR-008; contract procedure checked separately
Affected activityPartition installation A-120Baseline P-02; progress update P-03
MitigationTwo installers redeployed on 7 Oct; access restored 8 Oct 10:00TS-07/08
AssessmentTwo days requested; critical sequence and other causes require assessmentPlanner narrative PN-03; not an agreed EOT

Submission index

Scroll across if needed to read the whole record. A dash means no value has been entered.

Submission index: completed fictional example
SectionDocumentPurposeReviewer / status
1Event narrative NAR-02Facts, contract basis and requested reliefQS reviewed
2P-02 / P-03Baseline, actual progress and forecast comparisonPlanner to confirm logic
3AL-07/08, D-07/08, TS-07/08Access, site and resource recordsOriginal files retained

This record does not automatically convert idle hours or an activity delay into an extension of time. Cost recovery is a separate assessment.

Understanding your results

This record does not automatically convert idle hours or an activity delay into an extension of time. Cost recovery is a separate assessment.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.

If you need help preparing or reviewing the project records, our quantity surveying services explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.