Check the delay notice requirement promptly. Record the event and serve a compliant notice while you assemble the detail.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 1 min readShare
Why
A short message may not meet the required content or service rules. A notice alone does not prove entitlement to extra time or money, and the contract may require later particulars and updates.
How do I do it?
- Identify the event, its first known effect and the relevant notice clause.
- Use the required recipient, method, timing and content.
- Diarise the particulars and updates, keeping evidence of service.
Our Construction contract management maps each notice trigger and escalation route so analysis can continue without overlooking administration deadlines.