JCT contract cheat sheet for main contractors

Manage both sides of a JCT project: secure your own payment and changes while administering separate obligations to your subcontractors.

by Jack Butler-Kettle · About 5 min readShare

Before you start

Use this as a quick operational checklist, not a complete contract summary. Keep the signed form, amendments and project dates beside it.

For main contractors using JCT Standard Building Contract (SBC) or Design and Build (DB), including 2016 and 2024 editions. Other JCT forms differ. Read the Contract Particulars and amendments together. JCT's 2024 overview explains changes to communications and contract procedures.

Working in another role? See the sheet for subcontractors or clients.

Step-by-step guide

  1. 1. Map the main contract and each subcontract

    Do this: Confirm design responsibility, possession, completion dates and who can instruct. Under SBC, identify the contract administrator; under DB, identify the employer's agent and delegated authority.

    Watch for: Your obligations to a subcontractor may exceed what you can recover from the employer. Compare scope, dates and notice requirements before placing orders.

    Main-contract and subcontract administration support can help turn the agreed terms into a working diary of duties and notices.

  2. 2. Run separate payment diaries

    Do this: Submit the main-contract application with measurement and change support. Assess subcontract applications, serve required notices and arrange payment using each subcontract's timetable. Follow the JCT payment guide.

    Watch for: An employer's reduced assessment does not itself justify reducing a subcontract payment. Keep the valuation basis, notice obligation and cash forecast separate.

  3. 3. Connect instructions to both accounts

    Do this: Record authorised instructions against the original scope. Price additions and omissions, notify time effects and issue clear subcontract instructions. Reconcile the upstream and downstream change registers.

    Watch for: Recoverability from the employer and liability to the subcontractor are separate questions. Do not mark a change agreed merely because you submitted it.

  4. 4. Separate time entitlement from cost entitlement

    Do this: Give delay notices and supporting particulars promptly under the agreed procedure. Explain completion impact and mitigation. Identify Relevant Events for time and Relevant Matters for loss and expense.

    Watch for: The two lists differ. JCT's time and money guidance explains the distinction; check edition-specific changes and selected provisions.

  5. 5. Control handover, deductions and final agreement

    Do this: Record practical completion, sections, defects and outstanding documents. Reconcile retention and final accounts on both sides. Check certification, notices and extension decisions before applying delay damages.

    Watch for: Final-certificate challenge periods and settlement wording can close off claims. Keep unresolved items visible; use final-account checks before signing.

Before you finish: Write down the next action, its owner, deadline and delivery method. Get advice on uncertain rights before an irreversible step.

Worked example

The facts

Fictional example: a JCT contractor owes an assessed subcontract payment while its own variation remains disputed with the employer.

What happens

  1. The contractor checks the subcontract payment obligation and serves any required notices on time.

  2. It pays as required and pursues the separate main-contract variation with its instruction and valuation evidence.

What this shows

A disputed upstream change is not treated as an automatic defence to a different payment obligation.

JCT main contractor briefing template

Fill the blank briefing from the executed agreement and its amendments. Have the contractual contact, deadlines and responsibilities checked, then issue a dated version to the team.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Project and contract

Project / package
Westhaven refurbishment / internal works
Our role / party
Main contractor / Alder Mere Projects Ltd
Selected form / edition
JCT Design and Build 2024
Amendments / controlled copy
Signed contract plus amendments schedule rev 2, held in contract folder
Briefing owner / checked
Commercial lead; checked 14 October 2026; briefing revision 1
Contractual contact / route
Employer’s agent; named contact and notice category in signed communications schedule

Site-team operating sheet

Scroll across if needed to read the whole record. A dash means no value has been entered.

Site-team operating sheet: completed fictional example
AreaCompleted project briefingRecord / owner
Scope and authorityCoordinate the main works and interfaces. Keep each subcontract scope, notice route and recovery position separate from the main contract.Scope rev C; document register / project lead
PaymentMaintain separate main-contract and subcontract payment diaries. Assess each subcontract on its own terms; reconcile upstream and downstream positions.October application deadline 20 Oct 12:00; checked project diary / QS
ChangesRecord the authorised instruction and value the change under the agreed rules. Notify time and loss/expense effects through their separate procedures.CH-07: relocation instruction I-07; price and time unresolved / QS
Delay and recordsCheck the relevant grounds for time and money separately. Keep the delay notice, particulars, mitigation and completion assessment together.Access restriction 7–8 Oct; D-07/08, AL-07/08, programme P-02 / planner
CompletionTrack project and sectional completion, defects and both sets of final accounts. Check extension decisions and prerequisites before assessing delay damages.Handover HR-01; as-built drawing outstanding / project lead

Live actions and dates

Scroll across if needed to read the whole record. A dash means no value has been entered.

Live actions and dates: completed fictional example
ActionChecked project date / sourceOwner / evidence
Confirm CH-07 submission16 Oct 2026; review action, not a universal notice periodQS / issued submission and receipt
Submit October application20 Oct 2026 12:00; project payment schedule P rev 2Accounts lead / APP-10 and delivery proof
Resolve incomplete handover16 Oct 2026; close-out action CO-02Design lead / accepted as-built drawing

Fictional project briefing. Dates and responsibilities shown are illustrative project entries, not standard-form defaults. This original summary does not reproduce or replace the contract. Check every clause, recipient and deadline in the actual executed documents.