Information arrives late, areas aren't ready when promised, and my programme is being eaten by things I don't control.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
What does this mean for me?
Drawings turn up after the work needs them. An area isn't ready, or another trade is in the space you were promised. Often nobody gives an instruction at all. Your gangs, plant and sequence take the hit, and that effect needs recording while it can still be seen.
Your contract may give you a route to be paid for late information, access or possession. But the notice, the cause, the programme and the value are four separate questions. Each needs its own facts: what you asked for, when it was due, what arrived, where the team could work and what it did instead.
Leave it, and the cost disappears into your labour account. A claim rebuilt from memory months later is far easier to knock down. A short log kept as it happens ties each site event to the drawings, emails, access records and resources. It supports a later claim. It does not decide the delay, whether you are owed the money or how much.
What do I need to do?
- Log what was needed, when it was due, what arrived and which activity was affected.
- Record what the team did instead and retain the instructions, access records and programme evidence.
- Follow the contract's notice requirements promptly without waiting until the full cost is known.
- Keep resource and cost records linked to each event; obtain the appropriate specialist assessment of any effect on completion.
To have this done for you, see our Delay and disruption records setup, Delay and disruption cost recovery and Extension-of-time evidence preparation services.
If the hold-up has disrupted the gang and nobody can price it, see what to do when the disruption is real and has no number on it.