I've been told to speed up, at my own cost

The programme has slipped, the pressure is on, and I am being pushed into acceleration without anyone agreeing to pay for it.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

What does this mean for me?

A push to speed up, called acceleration, can mean overtime, weekend working, extra gangs or working out of sequence. It rarely arrives as a clear instruction. It comes as a comment in a meeting, a new target on the programme, or pressure to catch up. It may not say on whose authority, what is wanted or who pays.

Whether you get the cost back depends on your contract and on what caused the delay. It also depends on what you were asked to do, what else you could have done, and what you can prove you did. Acceleration, mitigation (the steps you take to keep a delay's cost down) and an ordinary catch-up plan are different things. Tell them apart from the facts, not from one remark in a meeting. Being pushed to hold your original date when you should have had more time is often called constructive acceleration.

Speed up on a verbal push and you may carry the cost of every extra gang and Saturday yourself. Later there may be nothing in writing to show who asked. And a cost figure on its own does not prove you are owed the money.

What do I need to do?

  1. Record the requested finish date, proposed measures, authority and payment basis before committing extra resources.
  2. Seek written agreement and involve the person responsible for programme assessment.
  3. Record additional costs and avoided costs separately from the outset.
  4. Keep the instruction, quotation, programme and daily records together, distinguishing acceleration from measures to recover your own delay.