What is a provisional sum, and how is the work valued?

A provisional sum is an allowance for work not fully described at tender, and the work is usually valued like a variation once instructed.

Updated: . By Jack Butler-Kettle, Construction Claims Consultant.

The answer

The sum sits in your price as a placeholder, not a promise of payment. Nothing is due against it until your main contractor instructs the work. Once it does, the work is valued under your subcontract's valuation rules, much as a variation is. The allowance comes out of the account and the valued work goes in, so the final figure can be higher or lower. Many contracts split provisional sums into two kinds. A defined provisional sum describes the work well enough for you to plan and price around it. An undefined one does not. The difference matters for your money. With a defined sum, you are usually treated as having allowed for its effect at tender. That covers its effect on your programme and your preliminaries, your site running costs. With an undefined sum, those effects can be valued in full when the work is instructed. A prime cost sum is different again: an allowance for work or goods from a named specialist or supplier. So when a provisional sum is instructed, treat it as a variation from day one. Put it on your variation register with the instruction date. Measure the work, keep daywork sheets for anything that cannot be measured, and price the effect on your preliminaries. Never let the allowance stand in the account as if it were the value of the work. Our Variation Claim service values provisional sum work under your subcontract's rules and presses it to agreement.

Example

Illustrative example. The scenario and figures are invented.

The facts

A mechanical subcontractor's price includes an undefined provisional sum of £15,000 for plant room connections still being designed. The main contractor instructs the work in month 5, and proposes to pay the £15,000 as it stands.

What happens

  1. The instruction goes on the variation register the day it arrives, with its date and the drawing it refers to.
  2. The subcontractor measures the pipework and valves at its rates: £19,800.
  3. The sum was undefined, so the extra supervision the work needs, £1,600, is priced in as well.
  4. The account takes out the £15,000 allowance and puts in the £21,400 valuation.

The provisional sum in figures

ItemAmount
Provisional sum in the price£15,000
Measured work at the subcontract rates£19,800
Extra supervision£1,600
Valued work£21,400
Net addition to the account£6,400

The outcome

The account moves up by £6,400, because the work was valued under the rules rather than paid at the allowance.

To have provisional sum work valued under your subcontract's rules, not paid at the allowance, see our Variation Claim service.