A provisional sum is an allowance for work not fully defined when the price is agreed. Its later instruction and valuation depend on the contract.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
A provisional sum is an allowance for work not fully defined when the price is agreed. Its later instruction and valuation depend on the contract.
It is not automatically a fixed price or an amount payable in full. Check what it covers, how it becomes authorised work and the applicable valuation procedure.
The RICS New Rules of Measurement, NRM 2 distinguishes defined and undefined provisional sums in its measurement framework. Check whether those rules are incorporated and how the contract treats them.
A defined sum supplies specified information about the work; an undefined sum does not meet that information basis. Programme and preliminaries consequences require the actual rules and evidence.
A prime cost or PC allowance is different. In some building quotations it allows for a specified supply item, with installation and additions priced separately. Definitions vary between contracts and measurement systems.
For a homeowner choosing finishes, check the quantity, allowance per unit, permitted additions and whether installation is included. A £30/m² tile allowance cannot establish the finished floor price on its own.
When an allowance is replaced, remove the superseded amount and insert the properly assessed replacement. A £10,000 allowance replaced by £13,000 creates a £3,000 movement on the same basis.
Keep the instruction, measurement, quotation and agreed valuation together. Do not treat a low provisional sum as proof that the final cost will stay low.
Our Variations and compensation events reconciles the allowance with the instructed scope and its contractual valuation.