Payment application checklist

Check the valuation date, required format, recipient, attachments and submission evidence before sending an application.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Complete against the actual contract requirements for that cycle. Leave a check open if its source or evidence is missing.

Payment application checklist

Complete against the actual contract requirements for that cycle. Leave a check open if its source or evidence is missing.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Payment application checklist

Scroll across if needed to read the whole record. A dash means no value has been entered.

Payment application checklist: completed fictional example
CheckCompleted exampleStatus / evidence
Correct cycle and versionAPP-10 r1; valuation to 20 Oct 2026Checked against payment schedule P rev 2
Valuation and arithmetic£120,000 gross less £6,000 retention and £90,000 previous assessment£24,000 current application; reviewed by QS
Required attachmentsMeasurement MW-10; change summary CH-10All listed in covering email
Recipient and timingPortal and accounts inbox specified in signed scheduleUpload planned before 20 Oct 12:00
Proof of issueKeep submitted workbook, PDFs and portal receiptOpen until receipt is saved

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the related guidance for the context and checks behind this template.