Project setup checklist

Check the agreed scope, contract documents, payment process and project responsibilities in one editable project setup record.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Complete this before starting work. Record the exact document and revision, who checked it and the action required for anything unresolved.

Project setup checklist

Complete this before starting work. Record the exact document and revision, who checked it and the action required for anything unresolved.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Project setup checklist

Scroll across if needed to read the whole record. A dash means no value has been entered.

Project setup checklist: completed fictional example
CheckAgreed position / sourceOwnerChecked onStatusAction / evidence
Signed agreementOrder WH-042 signed 1 Oct 2026; scope rev CCommercial lead2 Oct 2026VerifiedSigned PDF in contract folder
Design responsibilityScope section D: partition setting-out onlyDesign lead2 Oct 2026VerifiedNo structural design in package
Payment calendarSchedule P rev 2; application 20 Oct; final payment 16 NovAccounts lead2 Oct 2026VerifiedDiary entries PAY-01
Insurance evidenceRequired policy certificate not yet receivedCommercial lead2 Oct 2026OpenObtain current certificate by 5 Oct

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.