Skip to content

FIDIC subcontractor briefing template

Give the FIDIC subcontractor team a concise project briefing covering responsibilities, payment, changes, delay and close-out.

by Jack Butler-Kettle · About 4 min readShare

How to use it

Fill the blank briefing from the executed agreement and its amendments. Have the contractual contact, deadlines and responsibilities checked, then issue a dated version to the team.

FIDIC subcontractor briefing template

Fill the blank briefing from the executed agreement and its amendments. Have the contractual contact, deadlines and responsibilities checked, then issue a dated version to the team.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Project and contract

Project / package
Westhaven refurbishment / internal works
Our role / party
Subcontractor / Westhaven Interiors Ltd
Selected form / edition
FIDIC Conditions of Subcontract for Construction, 2011, with a 1999 Red Book main contract
Amendments / controlled copy
Signed contract plus amendments schedule rev 2, held in contract folder
Briefing owner / checked
Commercial lead; checked 14 October 2026; briefing revision 1
Contractual contact / route
Contractor’s named representative; named contact and notice category in signed communications schedule

Site-team operating sheet

Scroll across if needed to read the whole record. A dash means no value has been entered.

Site-team operating sheet: completed fictional example
AreaCompleted project briefingRecord / owner
Scope and authorityPartition package only; setting-out design included, structural design excluded. Obtain incorporated terms before relying on the briefing.Scope rev C; document register / project lead
PaymentSubmit a supported cumulative application under the subcontract. Record the assessment, deductions, final payment date and receipts.October application deadline 20 Oct 12:00; checked project diary / QS
ChangesRecord written instructions, the agreed valuation route and any separate claim or notice requirement. Check the actual Particular Conditions and amendments.CH-07: relocation instruction I-07; price and time unresolved / QS
Delay and recordsCheck the executed contract claim procedure, trigger and particulars requirements. Support time and cost separately with contemporary records.Access restriction 7–8 Oct; D-07/08, AL-07/08, programme P-02 / planner
CompletionRecord package completion, handover and defects. Check the subcontract retention release condition and final-account/challenge requirements.Handover HR-01; as-built drawing outstanding / project lead

Live actions and dates

Scroll across if needed to read the whole record. A dash means no value has been entered.

Live actions and dates: completed fictional example
ActionChecked project date / sourceOwner / evidence
Confirm CH-07 submission16 Oct 2026; review action, not a universal notice periodQS / issued submission and receipt
Submit October application20 Oct 2026 12:00; project payment schedule P rev 2Accounts lead / APP-10 and delivery proof
Resolve incomplete handover16 Oct 2026; close-out action CO-02Design lead / accepted as-built drawing

Fictional project briefing. Dates and responsibilities shown are illustrative project entries, not standard-form defaults. This original summary does not reproduce or replace the contract. Check every clause, recipient and deadline in the actual executed documents.

Understanding your results

Fictional project briefing. Dates and responsibilities shown are illustrative project entries, not standard-form defaults. This original summary does not reproduce or replace the contract. Check every clause, recipient and deadline in the actual executed documents.

How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the related guidance for the context and checks behind this template.

If you need help preparing or reviewing the project records, our quantity surveying services explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.

Browse the Library