Early warning register

Track notified risks, mitigation decisions and follow-up actions without confusing an early warning with a compensation-event notice.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Record the risk when identified, the communication reference and agreed mitigation. Manage any compensation event through its separate procedure.

Early warning register

Record the risk when identified, the communication reference and agreed mitigation. Manage any compensation event through its separate procedure.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Early warning register

Scroll across if needed to read the whole record. A dash means no value has been entered.

Early warning register: completed fictional example
Warning / dateRisk and possible effectCommunicationMitigation / decisionOwner / dueStatus / event link
EW-03 / 5 OctLevel 1 access may be unavailable; partition sequence at riskEW-03 portal receipt R-05Contractor to confirm access; prepare alternative work areaProject lead / 6 OctAccess subsequently unavailable; separate CE-02 issued
EW-04 / 9 OctDoor delivery forecast lateEW-04 receipt R-09Supplier to confirm dispatch and explore alternative stockBuyer / 12 OctOpen; no event decision recorded

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.

If you need help preparing or reviewing the project records, our quantity surveying services explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.