Early warning example

See a completed early-warning communication identifying a risk, its possible effect and proposed action.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Use the communication requirements in your actual NEC contract. An early warning manages risk; it is not a compensation-event notification.

Early warning example

Use the communication requirements in your actual NEC contract. An early warning manages risk; it is not a compensation-event notification.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Document details

Project
Westhaven refurbishment
From
Westhaven Interiors Ltd, commercial team
To
Alder Mere Projects Ltd, project commercial lead
Date
14 October 2026
Reference
WH-42-01

Early warning EW-03: potential restriction to Level 1 access

Project basis: fictional NEC4 ECC project. This communication is addressed by the Contractor to the named Project Manager through the agreed contract portal.

We have been advised that Level 1 access planned for 7 October may be unavailable. This could affect partition installation, increase resource costs and delay the following services work.

Please confirm the access arrangements. We propose an early-warning meeting on 6 October to consider release of another area and resequencing. Programme P-02 and the access plan are attached.

A compensation-event notification, if required, will be issued separately under the applicable contract procedure.

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the related guidance for the context and checks behind this template.