Float

The time an activity can move within a programme before affecting a defined successor or completion milestone, depending on the type of float being measured.

by Jack Butler-Kettle · About 2 min readShare

Further detail

Read this alongside SCL Delay and Disruption Protocol.

Float describes flexibility within a particular programme model. Total float concerns movement before the relevant overall completion or constrained milestone is affected; free float concerns movement before a successor is affected. State which measure is used. Programme float does not, by itself, decide which party may use it or whether time relief is due.

Check the current logic, calendars, constraints and actual progress before relying on a float figure. Read any contractual treatment of float alongside the programme and delay guidance. Where an event has commercial consequences, Delay and disruption cost recovery can address the supported cost position within the agreed scope.

Sources

  1. Delay and Disruption Protocol, 2nd edition, February 2017. Society of Construction Law.

Programme and progress example

Replace the simple sequence with the project programme and logic. Explain actual progress, remaining work, mitigation and other causes before assessing completion impact.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Programme and progress example

Scroll across if needed to read the whole record. A dash means no value has been entered.

Programme and progress example: completed fictional example
ActivityPredecessorBaseline startBaseline finishActual / forecast finishProgress evidenceAssessment
A-100 access releaseNone7 Oct 20267 Oct 20268 Oct 2026AL-07/08Access restored 8 Oct 10:00
A-120 partitionsA-1007 Oct 202612 Oct 202614 Oct 2026 forecastD-07/08; updated quantitiesResequencing partly mitigates interruption
A-140 servicesA-12013 Oct 202616 Oct 202618 Oct 2026 forecastPlanner update P-03Check available float and other constraints

This is an editable sequence illustration, not a critical-path analysis or a finding that an extension of time is due.