If time is at large, the fixed completion-date mechanism may no longer support the stipulated delay charge, but an obligation to finish within a reasonable time remains.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
If time is at large, the fixed completion-date mechanism may no longer support the stipulated delay charge, but an obligation to finish within a reasonable time remains. You then have to finish within a reasonable time instead.
The usual cause is the prevention principle. The other party cannot hold you to a date that its own acts stopped you meeting. Most contracts deal with that by letting the date be extended for the other party's own delays. So time goes at large only rarely. It can happen where the other party delays you and the clause gives no way to extend the date for it. If no fixed completion date was agreed, a reasonable-time obligation may instead arise from the agreement and law; that is not itself proof of prevention.
A delay you failed to notify, where the notice is a condition of any extension, usually does not set time at large. Whether time is at large on your job is a question for your solicitor.
The money point is simpler. A charge at the rate needs a completion date to count from. A general-damages claim must establish breach of the applicable completion obligation, causation and recoverable loss; absence of the original date does not automatically prove liability. In practice, most charges are won or lost on the ordinary points: the notices, the extensions granted and the arithmetic.
To have a delay damages charge tested against your notices, extensions and dates, see our Delay damages review and response service.