Reading each amendment beside the published clause it changes shows you which ones cost money. The schedule alone only shows which clauses changed.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
Parties often amend the published JCT and NEC forms with schedules that refer to clause numbers: delete this, substitute that, add a sub-clause. On their own they make little sense, so people skim them. Most are harmless. The few that are not can lengthen a payment period, turn a notice into a time bar or widen what can be deducted. In the schedule they look no different from a change of address.
How do I do it?
- Get a copy of the published form the contract is based on, and check that its edition matches the one the contract names.
- Go through the schedule in order, putting each amendment beside the clause it changes.
- Write one line for each: what it does to your money, your time or your risk, or no change.
- Mark each line high, medium or low by what it could cost on this job.
- Carry the high ones into your list of amendments to ask for, and the medium ones into your price.