They have sent a schedule of amendments and I cannot tell what it changes

The contract is a standard form with a long schedule of the other party's amendments, and nobody here has read the form it amends.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

What does this mean for me?

A contract based on a published JCT or NEC form may arrive with amendments. A JCT form gets a schedule of amendments. An NEC form gets additional conditions under Option Z. The schedule says which clause changes, but only by number, against a form you may not have on your desk. You cannot see what each change does until you read the two together.

The amendments that cost most are rarely the long ones. A single line can lengthen a payment period or turn a notice period into a time bar. Another can widen what the other party may deduct, or pass the main contract's risks down to you. Read one at a time, each looks reasonable. Together they can move a large part of the job's risk onto you.

Where amended wording is unclear, what it means in law is a question for your solicitor. What it does to your money and your programme is a commercial question, and you can answer it before you sign.

What do I need to do?

  1. Obtain the published form, correct edition and complete amendment schedule.
  2. Read each amendment beside the clause it changes. Record the effect on payment, notices, liability and programme obligations.
  3. Raise the important changes in writing, with the amendment you seek and its commercial reason.
  4. Check accepted changes in the final pack. Refer uncertain legal effects to your solicitor before accepting the remaining exposure.