A short, costed list of changes gets read and answered, while a list of forty objections tends to get a single reply: no. Rate each clause by its cost on this job, ask for the few that matter and price the rest.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
A long list of proposed contract changes is easy to refuse as a whole. A short list reads as a commercial case, with each item's cost to you and the wording you propose. Each item then gets decided on its merits. Put on it the clauses that move money or risk onto you in a way you cannot price. Typical ones are pay-when-paid wording, uncapped delay damages, set-off for losses on other contracts and time bars on notices.
How do I do it?
- List every clause that moves money or risk onto you, with a one-line note of what it does.
- Estimate what each could cost on this job: a financing cost for payment and retention terms, a realistic worst case for damages and deductions.
- Rate each high, medium or low, and pick the high ones.
- For each, write the wording you want and a fallback you would accept.
- Send them as one short schedule, and price the clauses you did not ask to change.