Check that your agreed exclusions are carried into the contract documents and order of precedence. Do not assume an earlier quotation will override conflicting terms.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
Your quote is priced on its exclusions and assumptions: no out of hours working, the other party's scaffold, a set number of visits. The contract often lists its own documents. It then adds a clause saying those documents are the whole agreement and replace everything that went before. If your quote is not on the list, its exclusions may not be part of the deal. The work you excluded then becomes an argument about whether it was ever priced. Whether a document left off the list still counts is a question for your solicitor. Getting it on the list before you sign avoids the question.
How do I do it?
- Find the contract's list of contract documents and any clause saying the contract is the whole agreement.
- Separate excluded work, pricing assumptions and alternative offers. State each precisely, with the relevant drawing, specification or package boundary.
- For example, state whether scaffold is provided by the contractor and what access period is assumed. Avoid a vague exclusion of all access costs.
- Check whether your quote, identified by its date and reference, or its exclusions and assumptions, are on the list.
- Ask for them to be added if they are not, or for the exclusions to be copied into a schedule of the contract.
- Check the order of precedence, which says which document wins when two disagree, so a specification or drawing cannot override the exclusions.
- Price the excluded items before you sign if the other party refuses.
- Retain the accepted clarification schedule with the final signed documents. Check every changed revision before treating earlier tender qualifications as agreed.
Our Construction contract review before signing checks whether tender qualifications survive in the proposed contract documents.