Calendar days, working days and the Construction Act's own count can put the same deadline on three different dates. Under the Act, weekends count but Christmas Day, Good Friday and bank holidays don't, so check which count each deadline uses.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
A 5 day period can end on three different dates. It depends on whether it is counted in calendar days, in working days or by the rule the law sets for construction contracts. The gap is usually a day or two, which is exactly the margin by which notices are missed. The trap is that one person reads the contract once and decides it is working days. Everyone then counts that way for the rest of the job. A notice counted in working days can land after a period that was really in calendar days. Nobody finds out until the miss has fixed a sum.
How do I do it?
- Read the definitions in the contract and note whether each payment period is in days, working days or business days.
- Check whether the contract says how days are counted. Then check whether the rule in section 116 of the Housing Grants, Construction and Regeneration Act 1996 applies to any of the periods.
- Write the counting rule against each deadline on the payment schedule so nobody has to remember it.
- Count out on a calendar, not in your head, any period that runs across a bank holiday or Christmas.
- Work to the earlier date wherever two readings give different ones.
Our Payment applications and valuations records the contractual counting rules beside each deadline so the timetable can be checked.