A payment diary copied from the last job or the standard form is wrong wherever the amendments moved a date. Build each contract's dates from its own signed wording, and record the clause and the trigger behind every one.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
A payment diary can miss a deadline or carry a standard-form date that an amendment has changed. One amendment moves the application date from the last Friday to the 25th. Another cuts a notice window from 5 days to 3, or names a new address for payment documents. Each change sits in a schedule of amendments nobody reread after signing. The diary looks complete and is wrong. The first sign is a payment notice that arrives before your application was due, or an application the payer says was late.
How do I do it?
- Collect the signed contract, its schedule of amendments and every document it makes part of the contract. Read the incorporated standard form with the executed amendments and document-priority provisions; do not rely on a superseded tender version.
- Record the clause behind each payment date, the event that triggers it, how the contract counts the days and how documents must be served.
- Write the action beside each date: who acts, who receives it, the form it takes and how it is sent.
- Keep your own early reminders separate from the contract deadline, so nobody mistakes an early target for the real date.
- Recheck the diary whenever an amendment, a new instruction or a changed address arrives.
Our Payment applications and valuations builds the payment routine around the executed terms rather than an assumed standard timetable.