Remediation scope changing behind the façade
The challenge
The external wall revealed on site may not match the investigation. Different cavity barriers, insulation or fixings can alter the remedial scope while scaffold and resident arrangements are already in place.
Our approach
We retain the survey assumptions and record specialist findings by location. Valuations can then distinguish the original remediation, newly instructed work and omissions. Where the scope grows, we also examine its effect on access duration and sequencing; adding a rate to the extra façade area may not capture the whole change.