Possessions and isolations shorter than planned
The challenge
A booked possession is not the same as productive working time. Late access, isolation or setup can consume a significant part of a short window.
Our approach
We compare the tender allowance with the actual possession chronology, including access, isolation, work and handback. That shows which activities lost time and whether they could move elsewhere. We then assess the evidenced standby, changed sequence or later return under the contract, rather than equating every lost hour with an hour of compensable delay.