A cap says how much you can spend, not how your work will be valued, so get the price basis written into the letter. Ask for your quoted rates, with a stated basis for anything the quote does not price.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
A letter of intent that states a cap and nothing else leaves the value of the work to be argued later. That usually happens once the relationship has soured. The other party will then pick the lowest figure it can defend: its own order price, another provider's rate, or the cap itself. Your quote shows what you asked for. It does not prove what was agreed. One sentence in the letter, tying the work to the rates in your dated quote, turns that later argument into arithmetic.
How do I do it?
- Check whether the letter says how the work will be valued. If it does not, note that as the first gap.
- Propose one sentence: the work is valued at the rates in your quote, identified by its date and reference.
- Propose a basis for work the quote does not price, such as daywork rates or cost plus a stated percentage.
- Keep the reply with the letter. If the point is refused, record it as open and price the risk before you start.
Our Letter-of-intent controls setup helps distinguish an authorised spending cap from the agreed basis for valuing the work.