Quantum meruit describes a reasonable payment for work or services. Whether that basis is available depends on the agreement and the circumstances.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 1 min readShare
The answer
Quantum meruit describes a reasonable payment for work or services. Whether that basis is available depends on the agreement and the circumstances. An unsigned contract, an expired letter of intent or an unpriced instruction does not automatically replace agreed terms with a cost-plus entitlement. First establish what was requested, what was agreed and whether an existing contract supplies a price or valuation mechanism. A reasonable-charge term within a contract and a restitutionary claim outside a contract have different legal foundations; ask your solicitor which, if either, applies.
For the valuation, measure the work actually provided and retain instructions, labour records, material invoices and comparable rates. Explain why the proposed allowance reflects reasonable value. Actual expenditure and a chosen profit percentage are evidence to examine, not an automatic price. Reconcile previous payments and avoid including the same work twice.
Valuing work done beyond the paper, on evidence, is our Payment recovery without a signed contract service.