Quotation basis and exclusions

Set out what a quotation includes, excludes and assumes, with the evidence needed to resolve pricing risks.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Issue this with the price and scope schedule. Make each qualification explicit and record whether it is accepted in the final agreement.

Quotation basis and exclusions

Issue this with the price and scope schedule. Make each qualification explicit and record whether it is accepted in the final agreement.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Quotation basis and exclusions

Scroll across if needed to read the whole record. A dash means no value has been entered.

Quotation basis and exclusions: completed fictional example
SubjectQuotation positionSource / allowanceAgreement / next action
ScopeInstall partitions shown on P-104 C onlyTender scope C; £80,000 packageClarify later drawing revisions
ExclusionStructural strengthening and asbestos removal excludedNo survey or design issuedClient to procure separately or obtain price
AccessContinuous weekday access assumedProgramme P-02; 08:00–17:00Confirm work-area release dates
Price validityOffer open until 30 Oct 2026Supplier quote Q-14 expires 30 OctReconfirm materials before order
Risk allowance£2,000 for defined restricted-access workingEstimate risk R-02Allowance is priced; no entitlement to spend twice

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the related guidance for the context and checks behind this template.