Notice and action diary

Track each contract deadline from its trigger to its checked date, responsible person and evidence of delivery.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Enter the actual contract rule and trigger; have the resulting deadline checked. This diary does not calculate legal deadlines or assume a standard notice period.

Notice and action diary

Enter the actual contract rule and trigger; have the resulting deadline checked. This diary does not calculate legal deadlines or assume a standard notice period.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Notice and action diary

Scroll across if needed to read the whole record. A dash means no value has been entered.

Notice and action diary: completed fictional example
Reference / actionTrigger and sourceVerified deadlineOwner / deputyDelivery routeIssued / proofStatus
N-01: change noticeInstruction I-07 received 7 Oct; agreed project diary D-029 Oct 2026, 16:00Commercial lead / project leadContract portal, notice category8 Oct 14:30; receipt R-008Delivered; response pending
PAY-01: applicationSchedule P rev 2, October cycle20 Oct 2026, 12:00QS / accounts leadNamed accounts inbox plus portalNot yet issuedDraft; check attachments by 19 Oct

Dates are invented project-specific diary entries, not JCT, NEC or FIDIC default periods. Keep the rule, date calculation and service evidence together.

Understanding your results

Dates are invented project-specific diary entries, not JCT, NEC or FIDIC default periods. Keep the rule, date calculation and service evidence together.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.