Instruction and change log

Connect an instruction to its scope, notice, pricing and time assessment in a single traceable change record.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Record the original instruction and baseline scope. Update the price and time positions separately; preserve each submission and reply.

Instruction and change log

Record the original instruction and baseline scope. Update the price and time positions separately; preserve each submission and reply.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Instruction and change log

Scroll across if needed to read the whole record. A dash means no value has been entered.

Instruction and change log: completed fictional example
Change / instructionBaseline and changed workAuthority / evidenceNoticePrice positionTime positionNext action / owner
CH-07 / I-07Drawing P-104 C to D; relocate 12 m partitionContractor project lead; portal I-07N-01 delivered 8 Oct£3,200 submitted; not agreed2 days forecast; not assessedQS to issue measured breakdown 14 Oct
CH-08 / I-08Add four access panelsWritten instruction 9 OctN-02 delivered 9 Oct£720 agreed 12 Oct, reply A-08No completion effect recordedAccounts to include in next application

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.