Final account preparation worksheet

Assemble the proposed final account and separate agreed changes, disputed items, retention and payments.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Reconcile the closing value with the change register before recording payments. Label proposals and agreements distinctly.

Final account preparation worksheet

Reconcile the closing value with the change register before recording payments. Label proposals and agreements distinctly.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Final account preparation worksheet

Scroll across if needed to read the whole record. A dash means no value has been entered.

Final account preparation worksheet: completed fictional example
AccountOriginal sum (£)Agreed changes (£)Unagreed claim (£)Proposed gross (£)Retention held (£)Payments received (£)Proposed balance (£)
WH-042 closing proposal£200,000.00£18,000.00£3,000.00£221,000.00£10,900.00£190,000.00£20,100.00

£221,000 is the proposed gross account, including £3,000 still disputed. £20,100 is the proposed balance excluding retention and VAT; it is not an agreed final payment.

Understanding your results

£221,000 is the proposed gross account, including £3,000 still disputed. £20,100 is the proposed balance excluding retention and VAT; it is not an agreed final payment.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.

If you need help preparing or reviewing the project records, our quantity surveying services explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.

Browse the Library