Final account covering letter

Submit a reconciled final account while identifying amounts that remain disputed or reserved.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Attach the actual account and evidence index. Match any reservation to the intended scope and obtain review before accepting final settlement wording.

Final account covering letter

Attach the actual account and evidence index. Match any reservation to the intended scope and obtain review before accepting final settlement wording.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Document details

Project
Westhaven refurbishment
From
Westhaven Interiors Ltd, commercial team
To
Alder Mere Projects Ltd, project commercial lead
Date
14 October 2026
Reference
WH-54-01

Subject: proposed final account FA-01

We submit final account FA-01 for order WH-042. The proposed gross value is £221,000 excluding VAT: £200,000 original sum, £18,000 agreed changes and £3,000 unresolved additional work.

Payments received total £190,000 and retention held is £10,900. The proposed balance excluding retention is £20,100. These figures are reconciled in the attached account and payment register.

The £3,000 item CH-12 remains disputed. Please provide your itemised response and supporting records. This submission is a proposal for assessment; it does not record acceptance of a general release or settlement of unspecified claims.

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

How it works

The Word file provides an unpopulated working structure to complete for your project. The completed fictional example stays on this page.

Read the related guidance for the context and checks behind this template.