Skip to content

Understand the items behind a settlement offer

Negotiate your final account item by item, because splitting the difference rewards whoever inflated their figure most. Trade weak items away for strong ones paid in full, and record what each concession bought as you go.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

Splitting the difference treats a fully evidenced £50,000 variation and a £50,000 guess as equal, and whoever guessed knows it. It is common because it feels fair and finishes quickly. But it rewards inflation and punishes honesty on every future account: the other side learns to claim high because it will be met halfway. Trading item by item keeps the strong items whole and gets something back for the weak ones. It also leaves a record of why each figure moved. That matters when a finance director or auditor later questions the settlement.

How do I do it?

  1. Rank every disputed item as strong, arguable or weak on the evidence before the meeting, with its value.
  2. Test an overall or percentage offer against the item analysis, costs and risks before deciding whether it is commercially acceptable.
  3. Concede weak items only in exchange for strong items being agreed in full, and say so when you do.
  4. Keep a running note of each item, the figure agreed and what it was traded against.
  5. Circulate the schedule promptly and seek confirmation of the actual agreement, its conditions and authority. A unilateral note does not make negotiations irrevocable.

Our Final account dispute assessment and response prepares an itemised negotiation position so concessions can be understood and recorded.

Browse completion and contract endings in the Library

Browse the Library