Skip to content

Know your range before the first meeting

Work out your final account's best, worst and likely outcomes, head by head, before anyone negotiates. The range tells you which concessions are cheap and which are surrender, and it is your only defence against a confident round number from the other side.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

The first number said aloud in a settlement meeting anchors everything after it. If the other side says it first, and says it confidently, you start measuring every concession against their figure, not the merits. Without a worst case, you cannot tell when to walk out. Without a likely case, you cannot tell whether an offer is good. Without a best case, you cannot tell what you are giving away. Built head by head from the evidence, the range turns a contest of nerve into a comparison of numbers.

How do I do it?

  1. Write the best, worst and likely outcome for each head, with reasons, uncertainties and possible adverse findings. A modelled worst case is not a guaranteed minimum; consider costs, timing and collectability too.
  2. Add the heads to give the account's best, worst and likely totals.
  3. Decide, before the meeting, the figure below which you will not settle, and who has authority to change it.
  4. Mark which heads are cheap to concede and which are the value of the account.
  5. Take the range into the meeting and test every offer against it before responding.

Our Final account dispute assessment and response assesses the evidence and disputed figures to support an informed settlement range.

Browse completion and contract endings in the Library

Browse the Library