The diary says the gang was moved but not where to

I can prove they were stopped. I can't prove what it cost, which is the half that pays.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

What does this mean for me?

The diary says the gang moved off block B, and stops there. Nobody recorded where they went, what they did instead, how long the interruption lasted or what it took to get going again. That entry records a reported move, but does not by itself establish compensable disruption. It cannot price it, and the price is the half that pays.

Work in the new area can be productive, partly productive or unproductive. Record which it was, rather than treating every move as the same loss. Cause without cost is sympathy, not money.

Recording the cost side is only a small addition to the diary habit you already have. It links the day's events to what they did to your resources. A later claim can then rest on records, not on rebuilding the story.

What do I need to do?

  1. Record the original work area, interruption, direction and time of each move.
  2. Record alternative work, output, return dates, double handling and any standing resources.
  3. Link the entries to daily labour and plant allocations.
  4. Assess net additional cost with productive alternative work, savings, other causes and possible overlap made explicit.

To have this done for you, see our Construction contract management service.

If the disruption is over and the number keeps collapsing, see what to do when the disruption is real and you can't put a number on it.