Check the notice that carried it, then ask in writing for its basis, evidence and build-up, and answer each line on what comes back.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 3 min readShare
Before you start
Have the deduction schedule, agreement, payment documents, service records and your site evidence ready. Identify any shorter contractual or procedural deadline before requesting more information.
Step-by-step guide
1. Identify the charge and payment position
Give each charge a reference and record the clause relied on, payment cycle, notice and amount. Keep the notice's effect on this payment separate from whether the underlying charge is ultimately due.
2. Request the basis and supporting records
Ask in writing for the calculation, invoices, timesheets, inspection records and evidence linking the cost to your work. Preserve handover records and photographs. A missing document raises a question but does not itself prove the charge wrong.
3. Test the amount and prepare your schedule
Check responsibility, scope, quantities, rates, credits and duplicate costs. Record what you accept, dispute or cannot yet assess, with the evidence and reason for each position. Reconcile the schedule to the actual deduction.
4. Respond and assess resolution options
Send the reasoned response within the applicable timetable and retain its issue record. If agreement fails, assess the available routes and cost. Section 108 of the Housing Grants, Construction and Regeneration Act 1996 provides an adjudication right for in-scope construction contracts. Check scope, procedure and any contractual right with your adviser before referring a dispute.
Before you finish: The schedule should distinguish accepted, disputed and unverified amounts, with a recorded response and next action for every open item.
Worked example
The facts
A painting subcontractor faces £18,000 of proposed contra-charges for scaffold adaptations, supervision and making good. They need a schedule showing where each item stands before they accept or dispute any of them.
What happens
The subcontractor records the clause relied on, the payment cycle and the notices for each item.
They ask for invoices, timesheets, inspection records and any credits.
As the evidence arrives, or fails to, they mark each item as accepted for now, disputed or awaiting advice.
They reconcile the schedule to £18,000, issue their reasoned response and record the evidence or advice needed before choosing a resolution route.
What this shows
The schedule shows how much of the £18,000 is accepted for now, disputed or awaiting advice, without guessing at settlement.
A missing document raises a question, but it does not prove the charge wrong.
Our Contra-charge review and challenge service challenges each deduction line by line for you.