Events keep landing on the job, and nobody is counting the weeks each one has left.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
What does this mean for me?
On an NEC job, events land before anyone has checked the notification rules that apply: late access, a changed drawing, a missing item. Your contract's form, options, amendments and Scope decide what starts the clock, who must notify, to whom, and how long you have. The familiar 8 weeks is not a safe substitute.
For each event you need a record: when you became aware and how you know, the clause used, proof of sending, and any exceptions. Notifying, quoting, pricing and time are related, but they are separate questions.
Miss a period and you may lose the change to your price and your dates. What a missed period actually costs you depends on your own contract, and needs proper advice.
What do I need to do?
- Record each event's awareness date and the evidence supporting it.
- Read the actual notification clause, amendments, recipient and communication requirements.
- Calculate the deadline from the applicable trigger and prioritise events closest to expiry.
- Retain notices and service evidence and escalate uncertain dates promptly rather than assuming the standard form's period applies.