Something happened on the job weeks ago, and we have only just realised the contract wanted it notified.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
What does this mean for me?
An event can sit on the job for weeks before anyone links it to the compensation event procedure. Think of the slab nobody expected, the late drawing, or the area handed over after the programme date. The commonly cited eight-week period comes from the NEC Engineering and Construction Contract (ECC). The Engineering and Construction Subcontract (ECS) commonly uses seven weeks. Identify your actual form, edition, amendments, trigger and exceptions before calculating a deadline.
Worrying does not answer the question. The awareness date, the exact clause and amendment, and whether the other party should have notified the event itself all decide whether the bar applies. Some of those are legal questions.
Two things make it worse: waiting, and sending a notification dated to look as if it went earlier than it did.
What do I need to do?
- Preserve the event and awareness evidence and read the notification clause and amendments immediately.
- If still in time, follow the required notification procedure without waiting for the full valuation.
- If the deadline may have passed, record the facts honestly and obtain advice on the actual consequence; never backdate the record.
- Keep the cost and programme evidence so the event can be assessed on a supported basis whichever way the time-bar question is resolved.
To have this done for you, see our NEC compensation event recovery and NEC compensation-event process setup services.