Skip to content

A letter of claim has arrived under the construction pre-action protocol. What do I do?

Where the Construction and Engineering Pre-Action Protocol applies, normally acknowledge within 14 days and respond within 28 days of receipt, subject to permitted agreement or exceptions. Send the letter to your solicitor promptly.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

The Pre-Action Protocol for Construction and Engineering Disputes sets steps for applicable proceedings in England and Wales, subject to its exceptions. It starts with a letter of claim. In it, the other party sets out its claim, the contract terms it relies on and the money it wants.

Your letter of response is due within 28 days of receiving it. The two sides can agree more time, but no more than 28 days extra for any step. Any objection should be raised within the same 28 days. That covers a claim sent to the wrong company, one that belongs in arbitration, or one the court cannot hear.

After your response, the two sides normally meet within 21 days to try to settle. The procedure is a question for your solicitor, so send the letter to them the day it arrives.

The figures are where you can do most. Test each head of the claim against your records, and mark what is accepted, disputed or unproven. Then add anything the other party owes you, such as an unpaid final account.

To have the claim tested head by head, and the figures for your letter of response built, see our Claim assessment and response service.

Sources

  1. Pre-Action Protocol for Construction and Engineering Disputes, second edition. Ministry of Justice.

Browse dispute resolution and defence in the Library

Browse the Library