Start with the contract's omission valuation rule. Then check committed materials, effects on remaining quantities and any separately recoverable cost; lost margin is not automatically retained.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
Removing work can create a contractual credit while leaving supplier commitments or changing how the remaining work is carried out. Identify each effect separately. The amount saved is useful evidence, but it does not universally replace the contract rate as the omission valuation.
Check whether the omission is within the contractual power, including any proposal to give the work to someone else. A legal claim for a wrongful omission is distinct from the valuation of an authorised omission. Neither route automatically preserves all overhead and profit on work no longer performed.
How do I do it?
- Identify the instruction, scope removed and applicable omission valuation provision.
- Calculate the contractual credit first, retaining the measurement and rates behind it.
- Record unavoidable cancellation, return or storage costs and reasonable mitigation, with the contractual basis for any additional claim.
- Check whether changed quantities permit a rate adjustment on the work remaining. Separate that calculation from any claim for wrongful omission and avoid double recovery.
Our Variation Recovery separates omitted scope, valuation adjustments and any disputed loss arising from the instruction.