A vesting certificate concerns ownership of identified goods. It does not, by itself, establish that their value must be paid in a particular application.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
Read the certificate with the contract's valuation and payment provisions. Check whether off-site materials qualify, which items are covered and what evidence or security is required. Do not assume that a document requested under the main contract changes your contract entitlement.
The NEC explanation of materials ownership distinguishes transfer of title from payment and discusses limits in the supply chain. Its ECC guidance is not a substitute for your contract or amendments. A certificate cannot safely be treated as proof of title that the transferring party does not have.
Keep an item schedule, supplier records, identification and storage evidence with the application. Check any required insurance, inspection, marking or bond against the actual terms. Seek legal advice on disputed ownership or certificate wording before signing assurances you cannot substantiate.
Our Subcontract payment assessments service checks the ordinary application against those conditions and records. Where materials have been excluded and the assessment is contested, Underpayment recovery examines the contractual valuation conditions, records and notices. That assessment keeps the ownership question distinct from what is payable in the cycle.
If you are a homeowner paying before delivery, check the same underlying questions rather than relying only on a document headed vesting certificate.
Confirm that the agreement permits payment for the identified goods, where they are stored and how they are separated from other orders. Check ownership evidence, insurance, access and delivery arrangements.
Ask about supplier retention-of-title terms or competing claims where relevant. Have legal effectiveness checked; a certificate does not automatically defeat every third-party right.
Reconcile the amount with deposits and previous valuations so the same materials are not paid twice. See builder deposit checks before agreeing an advance.