Not from the notified sum: a deduction already inside a valid payment notice needs no pay less notice, but taking money off the notified sum does.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
Under section 111 of the Housing Grants, Construction and Regeneration Act 1996, the payer must pay the notified sum by the final date for payment. The exception is a valid pay less notice that arrives in time. So first work out the notified sum from your contract and the notices actually sent, and compare it with what was paid.
Then look at the deduction itself. It may be part of the valuation under your contract, or a set-off, contra-charge or other counterclaim. Its label alone does not tell you which.
Record the shortfall and keep the documents before you choose your next step: a demand, a response on the valuation, a specialist review or a legal route. A missing notice does not automatically settle every issue. Nor does it, on its own, make suspending work the right move.
If money has landed short with no notice, Underpayment recovery assesses the notice and valuation so you can pursue the payment the evidence supports.