A cost to complete is one of the easiest figures in construction to inflate, so read it line by line against the scope in your own contract. Take out upgrades, other trades' work and extras before you argue about rates.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

The other party appoints the completion contractor in a hurry, on its own terms, to finish whatever it now wants. The price and invoices arrive as one figure, and that figure is set against you in the termination account. Inside it there is often work you were never asked to do. Look for betterment, meaning a better specification than yours. Look too for fire stopping from another package, making good other trades' damage, and changes the client instructed after you left. None of that is the cost of completing your work. The only way to find it is to read the completion documents against your scope, line by line, and list what does not belong separately.

How do I do it?

  1. Ask in writing for the completion contract, the quotes, the instructions to the completion contractor and its invoices.
  2. Set each line beside the item of your scope it completes, and mark any line with no matching item.
  3. Move betterment, other packages' work and later changes into their own schedule, with the reason for each.
  4. Answer the remaining lines on quantity and rate, and send the whole schedule back in your name.

Our Termination account preparation and assessment reconciles replacement costs with the original remaining scope, credits and evidence of additional expenditure.